FCE prepared a feasibility study on the Jordanelle Dam Powerplant for the Central Utah Water Conservancy District and Heber Light and Power.

This study was prepared to determine the most economical capacity and configuration of the powerplant and identify the quantity and cost of power to be produced.

Work involved preparing preliminary cost estimates for various powerplant sizes and configurations. Also, analyzed the operation of Jordanelle Reservoir, including available head and discharge, to determine the quantity of power that could be generated given the mechanical limitations of the units.

The recommended configuration for Jordanelle Dam Powerplant included two 5,200 horsepower horizontal Francis turbines coupled to a single 9,800 kilowatt generator.

Each turbine would have a design head of 226 feet and design flow of 230 cfs. A steel penstock, 72 inches in diameter and about 220 feet long, would be connected to an existing stubout located near the outlet tunnel portal.

The estimated construction cost of the project was $5.1 million. Per our study, when completed the powerplant would generate an average of 33,155,000 kilowatt-hours of energy per year.

We Know Water

We provide top-tier engineering
services to those who develop,
manage, and conserve this
precious resource.


©2013 Franson Civil Engineers.
All rights reserved.

Contact

1276 S. 820 E. 
Suite 100
American Fork, UT
84003

 

Toll Free: 888.756.3726
Office: 801.756.0309

 facebooktwitteryoutube